🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Virginia

SOLAR · PJM

Pigeon Run Solar and Storage

Pigeon Run Solar and Storage is a 60.0 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Campbell County, Virginia, connecting to Dominion.

Queue statusConsented
  1. PlanningQueued Mar 2019 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2031 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AE2-185
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Developer
Pigeon Run Solar, LLC
Connection point (POI)
Gladys DP-Stonemill Switching Station 69 kV
Location
Campbell County, Virginia
Technology
Solar: 60.0 MW
Total requested
60.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Active
Entered queue
18 March 2019
Proposed online date
March 2031

Location

Marker shows the centre of Campbell County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in Campbell County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem