United States βΊ Grid βΊ Interconnection queues βΊ Virginia
SOLAR Β· PJMSolar project AG1-276, Campbell County
Solar project AG1-276, Campbell County is a 20.0 MW solar request withdrawn in the PJM interconnection queue, in Campbell County, Virginia, connecting to Dominion.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2020 (completed)
- Withdrawn / abandonedFeb 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AG1-276
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- Gladys DP-Stone Mill 69 kV
- Location
- Campbell County, Virginia
- Technology
- Solar: 20.0 MW
- Total requested
- 20.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 28 September 2020
- Proposed online date
- March 2022
- Withdrawn
- February 2021
Location
Marker shows the centre of Campbell County; the queue data does not give exact sites.
Other requests in Campbell County
- Pigeon Run Solar and StorageSolar Β· 60.0 MW Β· agreement signed
- Gladys SolarSolar Β· 53.0 MW Β· agreement signed
- Solar + storage project AI1-178, Campbell CountySolar + storage Β· 80.0 MW Β· in study
- Altavista SolarSolar Β· 60.0 MW Β· built
- Altavista Power StationOther Β· 60.0 MW Β· built
- Altavista SolarSolar Β· 20.0 MW Β· built
- Solar project AE2-292, Campbell CountySolar Β· 127 MW Β· withdrawn
- Sugar Solar LLCSolar Β· 100 MW Β· withdrawn
- Solar + storage project AG1-316, Campbell CountySolar + storage Β· 75.0 MW Β· withdrawn
- Solar + storage project AH1-214, Campbell CountySolar + storage Β· 44.1 MW Β· withdrawn
- Battery storage project AH1-352, Campbell CountyBattery storage Β· 40.0 MW Β· withdrawn
- Battery storage project AH1-640, Campbell CountyBattery storage Β· 40.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem