United States › Grid › Interconnection queues › Virginia
OTHER · PJMAltavista Power Station
Altavista Power Station is a 60.0 MW other request built and operating in the PJM interconnection queue, in Campbell County, Virginia, connecting to Dominion.
Request details
- Queue ID
- X1-084
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- Altavista 115kV
- Location
- Campbell County, Virginia
- Technology
- Other: 60.0 MW
- Total requested
- 60.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
- Queue status
- Operational
- Entered queue
- 28 April 2011
- Agreement signed
- 7 June 2011
- Proposed online date
- December 2013
- Came online
- May 2013
Location
Marker shows the centre of Campbell County; the queue data does not give exact sites.
Other requests in Campbell County
- Pigeon Run Solar and StorageSolar · 60.0 MW · agreement signed
- Gladys SolarSolar · 53.0 MW · agreement signed
- Solar + storage project AI1-178, Campbell CountySolar + storage · 80.0 MW · in study
- Altavista SolarSolar · 60.0 MW · built
- Altavista SolarSolar · 20.0 MW · built
- Solar project AE2-292, Campbell CountySolar · 127 MW · withdrawn
- Sugar Solar LLCSolar · 100 MW · withdrawn
- Solar + storage project AG1-316, Campbell CountySolar + storage · 75.0 MW · withdrawn
- Solar + storage project AH1-214, Campbell CountySolar + storage · 44.1 MW · withdrawn
- Battery storage project AH1-352, Campbell CountyBattery storage · 40.0 MW · withdrawn
- Battery storage project AH1-640, Campbell CountyBattery storage · 40.0 MW · withdrawn
- Solar project AG1-276, Campbell CountySolar · 20.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem