SOLAR + STORAGE · PJMSolar + storage project AI1-178, Campbell County
Solar + storage project AI1-178, Campbell County is a 80.0 MW solar + storage request in interconnection study in the PJM interconnection queue, in Campbell County, Virginia, connecting to Dominion.
Queue statusIn planning
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AI1-178
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- Red House DP - Sugar Hill 115 kV
- Location
- Campbell County, Virginia
- Technology
- Solar: 80.0 MW · Battery
- Total requested
- 80.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Active
- Entered queue
- 9 September 2022
- Proposed online date
- December 2027
Location
Marker shows the centre of Campbell County; the queue data does not give exact sites.
Other requests in Campbell County
- Pigeon Run Solar and StorageSolar · 60.0 MW · agreement signed
- Gladys SolarSolar · 53.0 MW · agreement signed
- Altavista SolarSolar · 60.0 MW · built
- Altavista Power StationOther · 60.0 MW · built
- Altavista SolarSolar · 20.0 MW · built
- Solar project AE2-292, Campbell CountySolar · 127 MW · withdrawn
- Sugar Solar LLCSolar · 100 MW · withdrawn
- Solar + storage project AG1-316, Campbell CountySolar + storage · 75.0 MW · withdrawn
- Solar + storage project AH1-214, Campbell CountySolar + storage · 44.1 MW · withdrawn
- Battery storage project AH1-352, Campbell CountyBattery storage · 40.0 MW · withdrawn
- Battery storage project AH1-640, Campbell CountyBattery storage · 40.0 MW · withdrawn