SOLAR Β· PJM

Ho-Fel Solar

Ho-Fel Solar is a 40.0 MW solar request suspended in the PJM interconnection queue, in Isle Of Wight County, Virginia, connecting to Dominion.

Queue statusPaused / redesign
  1. PlanningQueued Sep 2018 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AE1-103
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Connection point (POI)
Holland-Union Camp 115 kV
Location
Isle Of Wight County, Virginia
Technology
Solar: 40.0 MW
Total requested
40.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Suspended
Entered queue
1 September 2018
Proposed online date
October 2026

Location

Marker shows the centre of Isle Of Wight County; the queue data does not give exact sites.

Power plants in Virginia Β· Transmission lines in Virginia

Other requests in Isle Of Wight County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem