Solar project AD2-207, Isle Of Wight County

Solar project AD2-207, Isle Of Wight County is a 100 MW solar request withdrawn in the PJM interconnection queue, in Isle Of Wight County, Virginia, connecting to Dominion.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2018 (completed)
  2. Withdrawn / abandonedApr 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AD2-207
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Connection point (POI)
Suffolk-Poe 115 kV
Location
Isle Of Wight County, Virginia
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
30 March 2018
Proposed online date
June 2020
Withdrawn
April 2018

Location

Marker shows the centre of Isle Of Wight County; the queue data does not give exact sites.