United States βΊ Grid βΊ Interconnection queues βΊ Virginia
SOLAR Β· PJMWindsor PVI
Windsor PVI is a 85.0 MW solar request suspended in the PJM interconnection queue, in Isle Of Wight County, Virginia, connecting to Dominion.
Queue statusPaused / redesign
- PlanningQueued Mar 2017 (current stage)
- ConsentedNov 2020 (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2023 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AC2-079
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- Ivor-Oak Ridge 115kV
- Location
- Isle Of Wight County, Virginia
- Technology
- Solar: 85.0 MW
- Total requested
- 85.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Suspended
- Entered queue
- 3 March 2017
- Agreement signed
- 2 November 2020
- Proposed online date
- June 2023
Location
Marker shows the centre of Isle Of Wight County; the queue data does not give exact sites.
Other requests in Isle Of Wight County
- Sycamore Cross SolarSolar Β· 240 MW Β· agreement signed
- Knoxville SolarSolar Β· 51.0 MW Β· agreement signed
- Knoxville SolarSolar Β· 20.0 MW Β· agreement signed
- Knoxville SolarSolar Β· 20.0 MW Β· agreement signed
- Solar + storage project AH1-216, Isle Of Wight CountySolar + storage Β· 99.0 MW Β· in study
- Ho-Fel SolarSolar Β· 40.0 MW Β· suspended
- CavalierSolar Β· 240 MW Β· built
- Solidago SolarSolar Β· 20.0 MW Β· built
- Solar + storage project AH1-645, Isle Of Wight CountySolar + storage Β· 450 MW Β· withdrawn
- Battery storage project AG2-350, Isle Of Wight CountyBattery storage Β· 250 MW Β· withdrawn
- Solar project AB2-042, Isle Of Wight CountySolar Β· 160 MW Β· withdrawn
- Solar project AD2-207, Isle Of Wight CountySolar Β· 100 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem