United States › Grid › Interconnection queues › Virginia
SOLAR · PJMSolar project AI1-011, Cumberland County
Solar project AI1-011, Cumberland County is a 46.0 MW solar request in interconnection study in the PJM interconnection queue, in Cumberland County, Virginia, connecting to Dominion.
Queue statusIn planning
- PlanningQueued Apr 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AI1-011
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- Buckingham- Farmville 230kV
- Location
- Cumberland County, Virginia
- Technology
- Solar: 46.0 MW
- Total requested
- 46.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Active
- Entered queue
- 1 April 2022
- Proposed online date
- December 2026
Location
Marker shows the centre of Cumberland County; the queue data does not give exact sites.
Other requests in Cumberland County
- Solar project AH2-350, Cumberland CountySolar · 150 MW · in study
- Solar project AG2-583, Cumberland CountySolar · 115 MW · in study
- Solar project AG2-151, Cumberland CountySolar · 100 MW · in study
- ACE Development Company, LLCSolar · 85.0 MW · in study
- Solar + storage project AH2-104, Cumberland CountySolar + storage · 72.0 MW · in study
- Solar + storage project AH2-013, Cumberland CountySolar + storage · 16.0 MW · in study
- Solar project AI1-126, Cumberland CountySolar · 10.0 MW · in study
- Solar project AG2-188, Cumberland CountySolar · 140 MW · withdrawn
- Energix Westmoreland LLCSolar · 100 MW · withdrawn
- ACE Development Company, LLCBattery storage · 34.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem