Solar + storage project AH2-104, Cumberland County

Solar + storage project AH2-104, Cumberland County is a 72.0 MW solar + storage request in interconnection study in the PJM interconnection queue, in Cumberland County, Virginia, connecting to Dominion.

Queue statusIn planning
  1. PlanningQueued Feb 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AH2-104
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Connection point (POI)
Willis Mts- Farmville 115kV
Location
Cumberland County, Virginia
Technology
Solar: 72.0 MW · Battery
Total requested
72.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Active
Entered queue
4 February 2022
Proposed online date
November 2024

Location

Marker shows the centre of Cumberland County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in Cumberland County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem