United States › Grid › Interconnection queues › Virginia
SOLAR · PJMSolar project AG2-151, Cumberland County
Solar project AG2-151, Cumberland County is a 100 MW solar request in interconnection study in the PJM interconnection queue, in Cumberland County, Virginia, connecting to Dominion.
Queue statusIn planning
- PlanningQueued Feb 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Feb 2024 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AG2-151
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Developer
- Cumberland Solar, LLC
- Connection point (POI)
- Trices Lake - James River Tap 115 kV
- Location
- Cumberland County, Virginia
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- System Impact Study
- Queue status
- Active
- Entered queue
- 14 February 2025
- Proposed online date
- February 2024
Location
Marker shows the centre of Cumberland County; the queue data does not give exact sites.
Other requests in Cumberland County
- Solar project AH2-350, Cumberland CountySolar · 150 MW · in study
- Solar project AG2-583, Cumberland CountySolar · 115 MW · in study
- ACE Development Company, LLCSolar · 85.0 MW · in study
- Solar + storage project AH2-104, Cumberland CountySolar + storage · 72.0 MW · in study
- Solar project AI1-011, Cumberland CountySolar · 46.0 MW · in study
- Solar + storage project AH2-013, Cumberland CountySolar + storage · 16.0 MW · in study
- Solar project AI1-126, Cumberland CountySolar · 10.0 MW · in study
- Solar project AG2-188, Cumberland CountySolar · 140 MW · withdrawn
- Energix Westmoreland LLCSolar · 100 MW · withdrawn
- ACE Development Company, LLCBattery storage · 34.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem