🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Virginia

BATTERY STORAGE · PJM

ACE Development Company, LLC

ACE Development Company, LLC is a 34.0 MW battery storage request withdrawn in the PJM interconnection queue, in Cumberland County, Virginia, connecting to Dominion.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2021 (completed)
  2. Withdrawn / abandonedJul 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AH1-440
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Developer
ACE Development Company, LLC
Connection point (POI)
Buckingham- Farmville 230kV
Location
Cumberland County, Virginia
Technology
Battery: 34.0 MW
Total requested
34.0 MW
Service type
Network resource (NRIS)
Study phase
In Progress (unknown study)
Queue status
Withdrawn
Entered queue
10 September 2021
Proposed online date
September 2026
Withdrawn
July 2025

Location

Marker shows the centre of Cumberland County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in Cumberland County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem