SOLAR · PJMSolar project AI2-244, Nottoway County
Solar project AI2-244, Nottoway County is a 50.3 MW solar request in interconnection study in the PJM interconnection queue, in Nottoway County, Virginia, connecting to Dominion.
Queue statusIn planning
- PlanningQueued Mar 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AI2-244
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- Victoria DP-Martin DP 115 kV
- Location
- Nottoway County, Virginia
- Technology
- Solar: 50.3 MW
- Total requested
- 50.3 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Active
- Entered queue
- 2 March 2023
- Proposed online date
- June 2028
Location
Marker shows the centre of Nottoway County; the queue data does not give exact sites.
Other requests in Nottoway County
- Solar project AE1-168, Nottoway CountySolar · 150 MW · withdrawn
- Solar project AG1-030, Nottoway CountySolar · 150 MW · withdrawn
- Solar project AG2-507, Nottoway CountySolar · 60.0 MW · withdrawn
- NW-Rocky Ford SolarSolar · 20.0 MW · withdrawn
- NW-Rocky Ford SolarSolar · 15.0 MW · withdrawn
- Solar project AG1-169, Nottoway CountySolar · 15.0 MW · withdrawn
- NW-Rocky Ford SolarSolar · 15.0 MW · withdrawn
- Battery storage project AG1-215, Nottoway CountyBattery storage · 14.0 MW · withdrawn
- Solar project AG1-170, Nottoway CountySolar · 10.0 MW · withdrawn
- Solar project AG1-345, Nottoway CountySolar · 8.0 MW · withdrawn
- Solar project AF2-399, Nottoway CountySolar · 5.2 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem