United States βΊ Grid βΊ Interconnection queues βΊ Virginia
SOLAR Β· PJMSolar project AG2-507, Nottoway County
Solar project AG2-507, Nottoway County is a 60.0 MW solar request withdrawn in the PJM interconnection queue, in Nottoway County, Virginia, connecting to Dominion.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2021 (completed)
- Withdrawn / abandonedDec 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AG2-507
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- Crewe - Victoria DP 115 kV
- Location
- Nottoway County, Virginia
- Technology
- Solar: 60.0 MW
- Total requested
- 60.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 31 March 2021
- Proposed online date
- December 2025
- Withdrawn
- December 2024
Location
Marker shows the centre of Nottoway County; the queue data does not give exact sites.
Other requests in Nottoway County
- Solar project AI2-244, Nottoway CountySolar Β· 50.3 MW Β· in study
- Solar project AE1-168, Nottoway CountySolar Β· 150 MW Β· withdrawn
- Solar project AG1-030, Nottoway CountySolar Β· 150 MW Β· withdrawn
- NW-Rocky Ford SolarSolar Β· 20.0 MW Β· withdrawn
- NW-Rocky Ford SolarSolar Β· 15.0 MW Β· withdrawn
- Solar project AG1-169, Nottoway CountySolar Β· 15.0 MW Β· withdrawn
- NW-Rocky Ford SolarSolar Β· 15.0 MW Β· withdrawn
- Battery storage project AG1-215, Nottoway CountyBattery storage Β· 14.0 MW Β· withdrawn
- Solar project AG1-170, Nottoway CountySolar Β· 10.0 MW Β· withdrawn
- Solar project AG1-345, Nottoway CountySolar Β· 8.0 MW Β· withdrawn
- Solar project AF2-399, Nottoway CountySolar Β· 5.2 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem