United States › Grid › Interconnection queues › Virginia

SOLAR · PJM

Cerulean Solar and Mulberry BESS

Cerulean Solar and Mulberry BESS is a 62.0 MW solar request in interconnection study in the PJM interconnection queue, in Richmond County, Virginia, connecting to Dominion.

Queue statusIn planning
  1. PlanningQueued Feb 2020 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2031 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AF2-120
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Developer
Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
Connection point (POI)
Garner-Northern Neck 115 kV
Location
Richmond County, Virginia
Technology
Solar: 62.0 MW
Total requested
62.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Interim Study
Queue status
Active
Entered queue
28 February 2020
Proposed online date
May 2031

Location

Marker shows the centre of Richmond County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in Richmond County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem