United States › Grid › Interconnection queues › Virginia
SOLAR · PJMBookers Mill Solar
Bookers Mill Solar is a 127 MW solar request built and operating in the PJM interconnection queue, in City Of Richmond County, Virginia, connecting to Dominion.
Request details
- Queue ID
- AE1-155
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- Garner-Northern Neck 115 kV
- Location
- City Of Richmond County, Virginia
- Technology
- Solar: 127 MW
- Total requested
- 127 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Operational
- Entered queue
- 26 September 2018
- Proposed online date
- May 2024
- Came online
- December 2024
Location
Marker shows the centre of City Of Richmond County; the queue data does not give exact sites.
Other requests in City Of Richmond County
- Cerulean Solar and Mulberry BESSBattery storage · 75.0 MW · agreement signed
- Battery storage project AI1-183, Richmond CountyBattery storage · 130 MW · in study
- Cerulean Solar and Mulberry BESSSolar · 62.0 MW · in study
- Moon Corner SolarSolar · 60.0 MW · in study
- BellemeadeGas · 22.0 MW · built
- Battery storage project AI1-031, Richmond CountyBattery storage · 100 MW · withdrawn
- Battery storage project AH2-026, City Of Richmond CountyBattery storage · 72.0 MW · withdrawn
- Solar project AF2-036, Richmond CountySolar · 62.0 MW · withdrawn
- Bermuda EnergyBattery storage · 19.1 MW · withdrawn
- Bermuda EnergyBattery storage · 19.1 MW · withdrawn
- Haynesville Energy StorageBattery storage · 10.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem