United States › Grid › Interconnection queues › Virginia
BATTERY STORAGE · PJMBattery storage project AI2-231A, Botetourt County
Battery storage project AI2-231A, Botetourt County is a 60.0 MW battery storage request in interconnection study in the PJM interconnection queue, in Botetourt County, Virginia, connecting to AEP.
Queue statusIn planning
- PlanningQueued Mar 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Oct 2023 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AI2-231A
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Cloverdale-Burlington Height 138 kV
- Location
- Botetourt County, Virginia
- Technology
- Battery: 60.0 MW
- Total requested
- 60.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Active
- Entered queue
- 2 March 2023
- Proposed online date
- October 2023
Location
Marker shows the centre of Botetourt County; the queue data does not give exact sites.
Other requests in Botetourt County
- Rocky Forge WindOnshore wind · 78.2 MW · agreement signed
- Gateway GridBattery storage · 100 MW · withdrawn
- Rocky Ford WFOnshore wind · 100 MW · withdrawn
- Onshore wind project AC1-227, Botetourt CountyOnshore wind · 96.6 MW · withdrawn
- Battery storage project AG1-240, Botetourt CountyBattery storage · 90.0 MW · withdrawn
- Onshore wind project AC2-003, Botetourt CountyOnshore wind · 78.0 MW · withdrawn
- Battery storage project AG1-155, Botetourt CountyBattery storage · 20.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem