BATTERY STORAGE Β· PJMBattery storage project AG1-240, Botetourt County
Battery storage project AG1-240, Botetourt County is a 90.0 MW battery storage request withdrawn in the PJM interconnection queue, in Botetourt County, Virginia, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2020 (completed)
- Withdrawn / abandonedDec 2020 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AG1-240
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Trinity 69 kV
- Location
- Botetourt County, Virginia
- Technology
- Battery: 90.0 MW
- Total requested
- 90.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 25 September 2020
- Proposed online date
- June 2024
- Withdrawn
- December 2020
Location
Marker shows the centre of Botetourt County; the queue data does not give exact sites.
Other requests in Botetourt County
- Rocky Forge WindOnshore wind Β· 78.2 MW Β· agreement signed
- Battery storage project AI2-231A, Botetourt CountyBattery storage Β· 60.0 MW Β· in study
- Gateway GridBattery storage Β· 100 MW Β· withdrawn
- Rocky Ford WFOnshore wind Β· 100 MW Β· withdrawn
- Onshore wind project AC1-227, Botetourt CountyOnshore wind Β· 96.6 MW Β· withdrawn
- Onshore wind project AC2-003, Botetourt CountyOnshore wind Β· 78.0 MW Β· withdrawn
- Battery storage project AG1-155, Botetourt CountyBattery storage Β· 20.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem