United States › Grid › Interconnection queues › Virginia
BATTERY STORAGE · PJMTavern Energy LLC
Tavern Energy LLC is a 50.0 MW battery storage request in interconnection study in the PJM interconnection queue, in Spotsylvania County, Virginia, connecting to Dominion.
Queue statusIn planning
- PlanningQueued Feb 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2024 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AH1-251
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Developer
- Tavern Energy, LLC
- Connection point (POI)
- Todds Tavern- Spotsylvania/Goldsdale 115kV
- Location
- Spotsylvania County, Virginia
- Technology
- Battery: 50.0 MW
- Total requested
- 50.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- System Impact Study
- Queue status
- Active
- Entered queue
- 18 February 2025
- Proposed online date
- December 2024
Location
Marker shows the centre of Spotsylvania County; the queue data does not give exact sites.
Other requests in Spotsylvania County
- Battery storage project AI1-018, Spotsylvania CountyBattery storage · 300 MW · in study
- Battery storage project AH1-263, Spotsylvania CountyBattery storage · 200 MW · in study
- Solar project AI2-038, Spotsylvania CountySolar · 150 MW · in study
- Spotsylvania Energy CenterSolar · 485 MW · built
- Solar project AE1-047, Spotsylvania CountySolar · 300 MW · withdrawn
- Solar project AD2-193, Spotsylvania CountySolar · 209 MW · withdrawn
- Solar project AG1-133, Spotsylvania CountySolar · 128 MW · withdrawn
- Solar project AH1-456, Spotsylvania CountySolar · 80.0 MW · withdrawn
- Battery storage project AG2-318, Spotsylvania CountyBattery storage · 75.0 MW · withdrawn
- Solar project AH1-250, Spotsylvania CountySolar · 60.0 MW · withdrawn
- Battery storage project AH1-457, Spotsylvania CountyBattery storage · 50.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem