United States › Grid › Interconnection queues › Virginia
SOLAR · PJMSolar project AI2-038, Spotsylvania County
Solar project AI2-038, Spotsylvania County is a 150 MW solar request in interconnection study in the PJM interconnection queue, in Spotsylvania County, Virginia, connecting to Dominion.
Queue statusIn planning
- PlanningQueued Jan 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AI2-038
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- St. Johns 115kV
- Location
- Spotsylvania County, Virginia
- Technology
- Solar: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Active
- Entered queue
- 25 January 2023
- Proposed online date
- December 2027
Location
Marker shows the centre of Spotsylvania County; the queue data does not give exact sites.
Other requests in Spotsylvania County
- Battery storage project AI1-018, Spotsylvania CountyBattery storage · 300 MW · in study
- Battery storage project AH1-263, Spotsylvania CountyBattery storage · 200 MW · in study
- Tavern Energy LLCBattery storage · 50.0 MW · in study
- Spotsylvania Energy CenterSolar · 485 MW · built
- Solar project AE1-047, Spotsylvania CountySolar · 300 MW · withdrawn
- Solar project AD2-193, Spotsylvania CountySolar · 209 MW · withdrawn
- Solar project AG1-133, Spotsylvania CountySolar · 128 MW · withdrawn
- Solar project AH1-456, Spotsylvania CountySolar · 80.0 MW · withdrawn
- Battery storage project AG2-318, Spotsylvania CountyBattery storage · 75.0 MW · withdrawn
- Solar project AH1-250, Spotsylvania CountySolar · 60.0 MW · withdrawn
- Battery storage project AH1-457, Spotsylvania CountyBattery storage · 50.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem