United States › Grid › Interconnection queues › Virginia

BATTERY STORAGE · PJM

Battery storage project AH1-263, Spotsylvania County

Battery storage project AH1-263, Spotsylvania County is a 200 MW battery storage request in interconnection study in the PJM interconnection queue, in Spotsylvania County, Virginia, connecting to Dominion.

Queue statusIn planning
  1. PlanningQueued Feb 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AH1-263
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Developer
Scarlet Energy Storage LLC
Connection point (POI)
Chancellor 115 kV
Location
Spotsylvania County, Virginia
Technology
Battery: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Active
Entered queue
13 February 2025
Proposed online date
June 2025

Location

Marker shows the centre of Spotsylvania County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in Spotsylvania County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem