SOLAR Β· PJM

Solar project AE1-047, Spotsylvania County

Solar project AE1-047, Spotsylvania County is a 300 MW solar request withdrawn in the PJM interconnection queue, in Spotsylvania County, Virginia, connecting to Dominion.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2018 (completed)
  2. Withdrawn / abandonedOct 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AE1-047
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Connection point (POI)
Spotsylvania 500 kV
Location
Spotsylvania County, Virginia
Technology
Solar: 300 MW
Total requested
300 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
11 July 2018
Proposed online date
November 2021
Withdrawn
October 2018

Location

Marker shows the centre of Spotsylvania County; the queue data does not give exact sites.

Power plants in Virginia Β· Transmission lines in Virginia

Other requests in Spotsylvania County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem