🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Virginia

BATTERY STORAGE · PJM

Battery storage project AJ1-001, Mecklenburg County

Battery storage project AJ1-001, Mecklenburg County is a 50.0 MW battery storage request in interconnection study in the PJM interconnection queue, in Mecklenburg County, Virginia, connecting to Dominion.

Queue statusIn planning
  1. PlanningQueued Apr 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AJ1-001
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Connection point (POI)
Boydton DP 115 kV
Location
Mecklenburg County, Virginia
Technology
Battery: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Active
Entered queue
21 April 2023
Proposed online date
December 2028

Location

Marker shows the centre of Mecklenburg County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in Mecklenburg County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem