Bluestone Farm Solar is a 49.9 MW solar request built and operating in the PJM interconnection queue, in Mecklenburg County, Virginia, connecting to Dominion.

Queue statusOperating
  1. PlanningQueued Feb 2016 (completed)
  2. ConsentedMay 2018 (completed)
  3. Construction (completed)
  4. OperatingApr 2021 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
AB2-043
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Connection point (POI)
Chase City 115kV
Location
Mecklenburg County, Virginia
Technology
Solar: 49.9 MW
Total requested
49.9 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Operational
Entered queue
29 February 2016
Agreement signed
23 May 2018
Proposed online date
April 2021
Came online
April 2021

Location

Marker shows the centre of Mecklenburg County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in Mecklenburg County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem