🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Virginia

SOLAR · PJM

Solar project AH1-227, Wise County

Solar project AH1-227, Wise County is a 51.3 MW solar request in interconnection study in the PJM interconnection queue, in Wise County, Virginia, connecting to AEP.

Queue statusIn planning
  1. PlanningQueued Feb 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AH1-227
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Developer
Virginia Electric and Power Company
Connection point (POI)
Flemming - Fremont 69 kV
Location
Wise County, Virginia
Technology
Solar: 51.3 MW
Total requested
51.3 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Active
Entered queue
27 February 2025
Proposed online date
December 2025

Location

Marker shows the centre of Wise County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in Wise County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem