ONSHORE WIND Β· SOUTHEAST

Onshore wind project LGE-GIS-2008-001, Wise County

Onshore wind project LGE-GIS-2008-001, Wise County is a 129 MW onshore wind request withdrawn in the Southeast interconnection queue, in Wise County, Virginia, connecting to Louisville Gas & Electric and Kentucky Utilities Energy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2008 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
LGE-GIS-2008-001
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Louisville Gas & Electric and Kentucky Utilities Energy
Connection point (POI)
LKEβ€šΓ„Γ΄s Old Dominion (ODP) system tapping the existing Arnold to Dorchester 161 kV line
Location
Wise County, Virginia
Technology
Wind: 129 MW
Total requested
129 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
14 March 2008
Proposed online date
December 2014

Location

Marker shows the centre of Wise County; the queue data does not give exact sites.

Power plants in Virginia Β· Transmission lines in Virginia

Other requests in Wise County