πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Virginia

SOLAR Β· SOUTHEAST

Solar project LGE-GIS-2021-021, Wise County

Solar project LGE-GIS-2021-021, Wise County is a 10.0 MW solar request withdrawn in the Southeast interconnection queue, in Wise County, Virginia, connecting to Louisville Gas & Electric and Kentucky Utilities Energy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2021 (completed)
  2. Withdrawn / abandonedOct 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
LGE-GIS-2021-021
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Louisville Gas & Electric and Kentucky Utilities Energy
Connection point (POI)
Dorchester - Bond 69 kV line
Location
Wise County, Virginia
Technology
Solar: 10.0 MW
Total requested
10.0 MW
Service type
Energy only (ERIS)
Queue status
Withdrawn
Entered queue
17 September 2021
Proposed online date
October 2023
Withdrawn
October 2021

Location

Marker shows the centre of Wise County; the queue data does not give exact sites.

Power plants in Virginia Β· Transmission lines in Virginia

Other requests in Wise County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem