Requests shown24052.5 GW
Active in queue52.5 GW240 requests
Agreement signed14.4 GW82 requests
Withdrawn467102.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

240 requests · page 3 of 5
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2017-133, Oklahoma County
Onshore wind
200 MWAgreement signed Oklahoma, OKSPP Nov 2017target 2030
Solar project GEN-2017-092, Muskogee County
Solar
200 MWAgreement signed Muskogee, OKSPP May 2017target 2026
Solar project GEN-2023-177, Garvin County
Solar
200 MWIn study Garvin, OKSPP Oct 2023target 2028
Battery storage project GEN-2024-120, Oklahoma County
Battery storage
199 MWIn study Oklahoma, OKSPP Mar 2025target 2028
Battery storage project GEN-2024-164, Murray County
Battery storage
199 MWIn study Murray, OKSPP Mar 2025target 2030
Battery storage project GEN-2024-187, Mcclain County
Battery storage
199 MWIn study Mcclain, OKSPP Mar 2025target 2029
Wind + storage project GEN-2024-308, Woodward County
Wind + storage
199 MWIn study Woodward, OKSPP Mar 2025target 2030
Battery storage project GEN-2024-250, Pittsburg County
Battery storage
199 MWIn study Pittsburg, OKSPP Mar 2025target 2029
Battery storage project GEN-2024-184, Atoka County
Battery storage
199 MWIn study Atoka, OKSPP Mar 2025target 2029
Battery storage project GEN-2024-318, Tulsa County
Battery storage
199 MWIn study Tulsa, OKSPP Mar 2025target 2028
Battery storage project GEN-2024-119, Cleveland County
Battery storage
199 MWIn study Cleveland, OKSPP Mar 2025target 2028
Battery storage project GEN-2024-245, Lincoln County
Battery storage
199 MWIn study Lincoln, OKSPP Mar 2025target 2029
Battery storage project GEN-2024-118, Wagoner County
Battery storage
199 MWIn study Wagoner, OKSPP Mar 2025target 2028
Solar + storage project GEN-2024-267, Bryan County
Solar + storage
195 MWIn study Bryan, OKSPP Mar 2025target 2029
Solar project GEN-2023-210, Lincoln County
Solar
191 MWIn study Lincoln, OKSPP Oct 2023target 2026
Solar project GEN-2024-158, Jackson County
Solar
190 MWIn study Jackson, OKSPP Mar 2025target 2029
Onshore wind project GEN-2016-133, Texas County
Onshore wind
188 MWAgreement signed Texas, OKSPP Nov 2016target 2029
Onshore wind project GEN-2016-134, Texas County
Onshore wind
188 MWAgreement signed Texas, OKSPP Nov 2016target 2029
Onshore wind project GEN-2016-138, Texas County
Onshore wind
188 MWAgreement signed Texas, OKSPP Nov 2016target 2029
Onshore wind project GEN-2016-137, Texas County
Onshore wind
188 MWAgreement signed Texas, OKSPP Nov 2016target 2029
Gas project ERAS-2025-003, Oklahoma County
Gas
186 MWIn study Oklahoma, OKSPP Sep 20252025
Battery storage project GEN-2025-SR14, Oklahoma County
Battery storage
183 MWIn study Oklahoma, OKSPP May 2025target 2030
Solar project GEN-2023-205, Hughes County
Solar
180 MWIn study Hughes, OKSPP Oct 2023target 2028
Battery storage project GEN-2022-136, Bryan County
Battery storage
180 MWIn study Bryan, OKSPP Feb 2023target 2030
Battery storage project GEN-2022-145, Johnston County
Battery storage
180 MWIn study Johnston, OKSPP Feb 2023target 2030
Battery storage project GEN-2024-SR5, Creek County
Battery storage
177 MWAgreement signed Creek, OKSPP Feb 2024target 2026
Onshore wind project GEN-2016-128, Alfalfa County
Onshore wind
176 MWAgreement signed Alfalfa, OKSPP Nov 2016target 2026
Onshore wind project GEN-2011-019, Woodward County
Onshore wind
175 MWAgreement signed Woodward, OKSPP Mar 2011target 2027
Onshore wind project GEN-2016-146, Texas County
Onshore wind
175 MWAgreement signed Texas, OKSPP Nov 2016target 2029
Onshore wind project GEN-2016-145, Texas County
Onshore wind
175 MWAgreement signed Texas, OKSPP Nov 2016target 2029
Solar project ERAS-2025-025, Caddo County
Solar
175 MWIn study Caddo, OKSPP Oct 2025target 2027
Solar + storage project GEN-2024-161, Jackson County
Solar + storage
170 MWIn study Jackson, OKSPP Mar 2025target 2030
Solar project GEN-2024-297, Mcintosh County
Solar
167 MWIn study Mcintosh, OKSPP Mar 2025target 2030
Solar project GEN-2024-296, Mcintosh County
Solar
167 MWIn study Mcintosh, OKSPP Mar 2025target 2030
Solar project GEN-2024-298, Mcintosh County
Solar
167 MWIn study Mcintosh, OKSPP Mar 2025target 2030
Onshore wind project GEN-2011-020, Ellis County
Onshore wind
166 MWAgreement signed Ellis, OKSPP Mar 2011target 2027
Solar project GEN-2017-140, Wagoner County
Solar
160 MWAgreement signed Wagoner, OKSPP Nov 2017target 2027
Solar + storage project GEN-2024-219, Murray County
Solar + storage
160 MWIn study Murray, OKSPP Mar 2025target 2030
Solar + storage project GEN-2024-360, Seminole County
Solar + storage
160 MWIn study Seminole, OKSPP Mar 2025target 2029
Solar project GEN-2019-045, Woods County
Solar
155 MWAgreement signed Woods, OKSPP May 2019target 2028
Solar + storage project GEN-2021-063, Mccurtain County
Solar + storage
155 MWIn study Mccurtain, OKSPP Apr 2021target 2027
Solar project GEN-2017-011, Ellis County
Solar
152 MWAgreement signed Ellis, OKSPP May 2017target 2026
Battery storage project GEN-2018-072, Kay County
Battery storage
151 MWAgreement signed Kay, OKSPP Oct 2018target 2027
Battery storage project GEN-2018-071, Kay County
Battery storage
151 MWAgreement signed Kay, OKSPP Oct 2018target 2027
Battery storage project GEN-2022-235, Canadian County
Battery storage
150 MWIn study Canadian, OKSPP Feb 2023target 2028
Battery storage project GEN-2024-244, Texas County
Battery storage
150 MWIn study Texas, OKSPP Mar 2025target 2029
Battery storage project GEN-2023-057, Pawnee County
Battery storage
150 MWIn study Pawnee, OKSPP Oct 2023target 2028
Solar project GEN-2017-171, Comanche County
Solar
150 MWAgreement signed Comanche, OKSPP Nov 2017target 2027
Battery storage project GEN-2022-238, Pottawatomie County
Battery storage
150 MWIn study Pottawatomie, OKSPP Feb 2023target 2028
Battery storage project GEN-2024-029, Logan County
Battery storage
150 MWIn study Logan, OKSPP Oct 2024target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)