Solar project ERAS-2025-025, Caddo County

Solar project ERAS-2025-025, Caddo County is a 175 MW solar request in interconnection study in the SPP interconnection queue, in Caddo County, Oklahoma, connecting to WFEC.

Queue statusIn planning
  1. PlanningQueued Oct 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
ERAS-2025-025
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WFEC
Connection point (POI)
Washita 138kV Substation
Location
Caddo County, Oklahoma
Technology
Solar: 175 MW
Total requested
175 MW
Service type
NRIS and ERIS
Study phase
ERAS
Queue status
Active
Entered queue
2 October 2025
Proposed online date
December 2027

Location

Marker shows the centre of Caddo County; the queue data does not give exact sites.

Power plants in Oklahoma · Transmission lines in Oklahoma

Other requests in Caddo County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem