Onshore wind project GEN-2016-091, Caddo County

Onshore wind project GEN-2016-091, Caddo County is a 304 MW onshore wind request built and operating in the SPP interconnection queue, in Caddo County, Oklahoma, connecting to AEP.

Queue statusOperating
  1. PlanningQueued Oct 2016 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJan 2022 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2016-091
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
AEP
Connection point (POI)
Gracemont-Lawton East Side 345kV
Location
Caddo County, Oklahoma
Technology
Wind: 304 MW
Total requested
304 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/COMMERCIAL OPERATION
Queue status
Operational
Entered queue
3 October 2016
Proposed online date
January 2022
Came online
January 2022

Location

Marker shows the centre of Caddo County; the queue data does not give exact sites.

Power plants in Oklahoma · Transmission lines in Oklahoma

Other requests in Caddo County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem