United States › Grid › Interconnection queues › Oklahoma
BATTERY STORAGE · SPPBattery storage project GEN-2024-318, Tulsa County
Battery storage project GEN-2024-318, Tulsa County is a 199 MW battery storage request in interconnection study in the SPP interconnection queue, in Tulsa County, Oklahoma, connecting to AEP.
Queue statusIn planning
- PlanningQueued Mar 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2024-318
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Tulsa North - American Airlines 138 kV Line
- Location
- Tulsa County, Oklahoma
- Technology
- Battery: 199 MW
- Total requested
- 199 MW
- Service type
- NRIS and ERIS
- Study phase
- DISIS STAGE
- Queue status
- Active
- Entered queue
- 1 March 2025
- Proposed online date
- December 2028
Location
Marker shows the centre of Tulsa County; the queue data does not give exact sites.
Other requests in Tulsa County
- Battery storage project GEN-2018-028, Tulsa CountyBattery storage · 200 MW · agreement signed
- Battery storage project GEN-2018-027, Tulsa CountyBattery storage · 100 MW · agreement signed
- Battery storage project GEN-2024-171, Tulsa CountyBattery storage · 250 MW · in study
- Other project GEN-2025-SR25, Tulsa CountyOther · 200 MW · in study
- Other project GEN-2025-SR21, Tulsa CountyOther · 100 MW · in study
- Gas project GEN-2005-024, Tulsa CountyGas · 181 MW · built
- Gas project GEN-2010-055, Tulsa CountyGas · 4.5 MW · built
- Onshore wind project GEN-2024-130, Tulsa CountyOnshore wind · 1,900 MW · withdrawn
- Onshore wind project GEN-2024-131, Tulsa CountyOnshore wind · 1,100 MW · withdrawn
- Solar project GEN-2022-167, Tulsa CountySolar · 250 MW · withdrawn
- Solar project GEN-2024-270, Tulsa CountySolar · 250 MW · withdrawn
- Gas project GEN-2005-023, Tulsa CountyGas · 172 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem