Other project GEN-2025-SR21, Tulsa County

Other project GEN-2025-SR21, Tulsa County is a 100 MW other request in interconnection study in the SPP interconnection queue, in Tulsa County, Oklahoma, connecting to AEP.

Queue statusIn planning
  1. PlanningQueued Jun 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2025-SR21
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
AEP
Connection point (POI)
Tulsa Power Station 138kV Substation
Location
Tulsa County, Oklahoma
Technology
Other: 100 MW
Total requested
100 MW
Service type
Energy only (ERIS)
Study phase
IA PENDING
Queue status
Active
Entered queue
12 June 2025
Proposed online date
May 2028

Location

Marker shows the centre of Tulsa County; the queue data does not give exact sites.

Power plants in Oklahoma · Transmission lines in Oklahoma

Other requests in Tulsa County