🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Oklahoma

SOLAR + STORAGE · SPP

Solar + storage project GEN-2024-267, Bryan County

Solar + storage project GEN-2024-267, Bryan County is a 195 MW solar + storage request in interconnection study in the SPP interconnection queue, in Bryan County, Oklahoma, connecting to WFEC.

Queue statusIn planning
  1. PlanningQueued Mar 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2024-267
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WFEC
Connection point (POI)
Durantp4 - Sclmnjc4 138 kV Line
Location
Bryan County, Oklahoma
Technology
Solar: 195 MW · Battery
Total requested
195 MW
Service type
NRIS and ERIS
Study phase
DISIS STAGE
Queue status
Active
Entered queue
1 March 2025
Proposed online date
March 2029

Location

Marker shows the centre of Bryan County; the queue data does not give exact sites.

Power plants in Oklahoma · Transmission lines in Oklahoma

Other requests in Bryan County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem