United States › Grid › Interconnection queues › Oklahoma
SOLAR · SPPSolar project GEN-2022-104, Bryan County
Solar project GEN-2022-104, Bryan County is a 113 MW solar request in interconnection study in the SPP interconnection queue, in Bryan County, Oklahoma, connecting to WFEC.
Queue statusIn planning
- PlanningQueued Jan 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2022-104
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- WFEC
- Connection point (POI)
- Brown - South Coleman Junction 138kV line
- Location
- Bryan County, Oklahoma
- Technology
- Solar: 113 MW
- Total requested
- 113 MW
- Service type
- NRIS and ERIS
- Study phase
- FACILITY STUDY STAGE
- Queue status
- Active
- Entered queue
- 26 January 2023
- Proposed online date
- June 2028
Location
Marker shows the centre of Bryan County; the queue data does not give exact sites.
Other requests in Bryan County
- Battery storage project GEN-2021-001, Bryan CountyBattery storage · 100 MW · agreement signed
- Solar project GEN-2017-232, Bryan CountySolar · 52.2 MW · agreement signed
- Solar + storage project GEN-2024-267, Bryan CountySolar + storage · 195 MW · in study
- Battery storage project GEN-2022-136, Bryan CountyBattery storage · 180 MW · in study
- Battery storage project GEN-2024-204, Bryan CountyBattery storage · 100 MW · in study
- Battery storage project GEN-2024-SR13, Bryan CountyBattery storage · 52.2 MW · in study
- Gas project GEN-2017-043, Bryan CountyGas · 1,550 MW · withdrawn
- Gas project GEN-2017-042, Bryan CountyGas · 1,100 MW · withdrawn
- Gas project GEN-2019-034, Bryan CountyGas · 120 MW · withdrawn
- Battery storage project GEN-2023-214, Bryan CountyBattery storage · 100 MW · withdrawn
- Battery storage project GEN-2023-207, Bryan CountyBattery storage · 50.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem