Onshore wind project GEN-2017-133, Oklahoma County

Onshore wind project GEN-2017-133, Oklahoma County is a 200 MW onshore wind request with a signed interconnection agreement in the SPP interconnection queue, in Oklahoma County, Oklahoma, connecting to OGE.

Queue statusConsented
  1. PlanningQueued Nov 2017 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2030 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2017-133
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OGE
Connection point (POI)
Arcadia 345kV
Location
Oklahoma County, Oklahoma
Technology
Wind: 200 MW
Total requested
200 MW
Service type
NRIS and ERIS
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
22 November 2017
Proposed online date
June 2030

Location

Marker shows the centre of Oklahoma County; the queue data does not give exact sites.