🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Oklahoma

BATTERY STORAGE · SPP

Battery storage project GEN-2018-029, Oklahoma County

Battery storage project GEN-2018-029, Oklahoma County is a 100 MW battery storage request with a signed interconnection agreement in the SPP interconnection queue, in Oklahoma County, Oklahoma, connecting to OGE.

Queue statusConsented
  1. PlanningQueued May 2018 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget May 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2018-029
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OGE
Connection point (POI)
Horseshoe Lake 138kV Substation
Location
Oklahoma County, Oklahoma
Technology
Battery: 100 MW
Total requested
100 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
29 May 2018
Proposed online date
May 2028

Location

Marker shows the centre of Oklahoma County; the queue data does not give exact sites.

Power plants in Oklahoma · Transmission lines in Oklahoma

Other requests in Oklahoma County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem