🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Oklahoma

GAS · SPP

Gas project GEN-2024-GR1, Oklahoma County

Gas project GEN-2024-GR1, Oklahoma County is a 492 MW gas request with a signed interconnection agreement in the SPP interconnection queue, in Oklahoma County, Oklahoma, connecting to OG&E.

Queue statusConsented
  1. PlanningQueued Jan 2024 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2024-GR1
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OG&E
Connection point (POI)
Horseshoe Lake 138kV
Location
Oklahoma County, Oklahoma
Technology
Gas: 492 MW
Total requested
492 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
8 January 2024
Proposed online date
December 2026

Location

Marker shows the centre of Oklahoma County; the queue data does not give exact sites.

Power plants in Oklahoma · Transmission lines in Oklahoma

Other requests in Oklahoma County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem