United States › Grid › Interconnection queues › Oklahoma
BATTERY STORAGE · SPPBattery storage project GEN-2024-244, Texas County
Battery storage project GEN-2024-244, Texas County is a 150 MW battery storage request in interconnection study in the SPP interconnection queue, in Texas County, Oklahoma, connecting to SPS.
Queue statusIn planning
- PlanningQueued Mar 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2024-244
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- SPS
- Connection point (POI)
- Sooner 115 kV Substation
- Location
- Texas County, Oklahoma
- Technology
- Battery: 150 MW
- Total requested
- 150 MW
- Service type
- NRIS and ERIS
- Study phase
- DISIS STAGE
- Queue status
- Active
- Entered queue
- 1 March 2025
- Proposed online date
- December 2029
Location
Marker shows the centre of Texas County; the queue data does not give exact sites.
Other requests in Texas County
- Onshore wind project GEN-2016-141, Texas CountyOnshore wind · 350 MW · agreement signed
- Onshore wind project GEN-2016-142, Texas CountyOnshore wind · 350 MW · agreement signed
- Onshore wind project GEN-2016-133, Texas CountyOnshore wind · 188 MW · agreement signed
- Onshore wind project GEN-2016-134, Texas CountyOnshore wind · 188 MW · agreement signed
- Onshore wind project GEN-2016-138, Texas CountyOnshore wind · 188 MW · agreement signed
- Onshore wind project GEN-2016-137, Texas CountyOnshore wind · 188 MW · agreement signed
- Onshore wind project GEN-2016-146, Texas CountyOnshore wind · 175 MW · agreement signed
- Onshore wind project GEN-2016-145, Texas CountyOnshore wind · 175 MW · agreement signed
- Solar project GEN-2017-100, Texas CountySolar · 103 MW · agreement signed
- Onshore wind project GEN-2016-139, Texas CountyOnshore wind · 100 MW · agreement signed
- Onshore wind project GEN-2007-046, Texas CountyOnshore wind · 200 MW · built
- Gas project GEN-2024-127, Texas CountyGas · 1,300 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem