United States › Grid › Interconnection queues › Oklahoma
BATTERY STORAGE · SPPBattery storage project GEN-2024-184, Atoka County
Battery storage project GEN-2024-184, Atoka County is a 199 MW battery storage request in interconnection study in the SPP interconnection queue, in Atoka County, Oklahoma, connecting to AEP.
Queue statusIn planning
- PlanningQueued Mar 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jan 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2024-184
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Atoka to Lehigh 138 kV Line
- Location
- Atoka County, Oklahoma
- Technology
- Battery: 199 MW
- Total requested
- 199 MW
- Service type
- NRIS and ERIS
- Study phase
- DISIS STAGE
- Queue status
- Active
- Entered queue
- 1 March 2025
- Proposed online date
- January 2029
Location
Marker shows the centre of Atoka County; the queue data does not give exact sites.
Other requests in Atoka County
- Solar project GEN-2024-316, Atoka CountySolar · 300 MW · in study
- Solar + storage project GEN-2023-069, Atoka CountySolar + storage · 100 MW · in study
- Solar project GEN-2019-015, Atoka CountySolar · 72.6 MW · withdrawn
- Solar + storage project GEN-2023-070, Atoka CountySolar + storage · 50.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem