BATTERY STORAGE · SPP

Battery storage project GEN-2024-184, Atoka County

Battery storage project GEN-2024-184, Atoka County is a 199 MW battery storage request in interconnection study in the SPP interconnection queue, in Atoka County, Oklahoma, connecting to AEP.

Queue statusIn planning
  1. PlanningQueued Mar 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2024-184
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
AEP
Connection point (POI)
Atoka to Lehigh 138 kV Line
Location
Atoka County, Oklahoma
Technology
Battery: 199 MW
Total requested
199 MW
Service type
NRIS and ERIS
Study phase
DISIS STAGE
Queue status
Active
Entered queue
1 March 2025
Proposed online date
January 2029

Location

Marker shows the centre of Atoka County; the queue data does not give exact sites.