United States › Grid › Interconnection queues › Oklahoma

SOLAR + STORAGE · SPP

Solar + storage project GEN-2023-069, Atoka County

Solar + storage project GEN-2023-069, Atoka County is a 100 MW solar + storage request in interconnection study in the SPP interconnection queue, in Atoka County, Oklahoma, connecting to WFEC.

Queue statusIn planning
  1. PlanningQueued Oct 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2023-069
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WFEC
Connection point (POI)
Tupelo - Atoka 138 kV Line
Location
Atoka County, Oklahoma
Technology
Solar: 100 MW · Battery
Total requested
100 MW
Service type
NRIS and ERIS
Study phase
FACILITY STUDY STAGE
Queue status
Active
Entered queue
2 October 2023
Proposed online date
September 2028

Location

Marker shows the centre of Atoka County; the queue data does not give exact sites.

Power plants in Oklahoma · Transmission lines in Oklahoma

Other requests in Atoka County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem