🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Oklahoma

BATTERY STORAGE · SPP

Battery storage project GEN-2024-119, Cleveland County

Battery storage project GEN-2024-119, Cleveland County is a 199 MW battery storage request in interconnection study in the SPP interconnection queue, in Cleveland County, Oklahoma, connecting to WFEC.

Queue statusIn planning
  1. PlanningQueued Mar 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2024-119
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WFEC
Connection point (POI)
Lexington 138 kV Substation
Location
Cleveland County, Oklahoma
Technology
Battery: 199 MW
Total requested
199 MW
Service type
NRIS and ERIS
Study phase
DISIS STAGE
Queue status
Active
Entered queue
1 March 2025
Proposed online date
December 2028

Location

Marker shows the centre of Cleveland County; the queue data does not give exact sites.

Power plants in Oklahoma · Transmission lines in Oklahoma

Other requests in Cleveland County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem