🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Oklahoma

BATTERY STORAGE · SPP

Battery storage project GEN-2021-088, Cleveland County

Battery storage project GEN-2021-088, Cleveland County is a 100 MW battery storage request in interconnection study in the SPP interconnection queue, in Cleveland County, Oklahoma, connecting to OGE.

Queue statusIn planning
  1. PlanningQueued Apr 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2021-088
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OGE
Connection point (POI)
Cedar Lane - Canadian 138 kV Transmission Line
Location
Cleveland County, Oklahoma
Technology
Battery: 100 MW
Total requested
100 MW
Service type
NRIS and ERIS
Study phase
FACILITY STUDY STAGE
Queue status
Active
Entered queue
29 April 2021
Proposed online date
January 2027

Location

Marker shows the centre of Cleveland County; the queue data does not give exact sites.

Power plants in Oklahoma · Transmission lines in Oklahoma

Other requests in Cleveland County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem