Other project J1490, Randolph County Other |
1,000 MW | Agreement signed |
Randolph, MO | MISO |
Apr 2019 | target 2024 |
Replacing 749 MW of coal generation with BESS; Campbell 3 Other |
749 MW | In study |
Ottawa, MI | MISO |
Nov 2023 | target 2028 |
Replacing 710 MW of coal generation with solar at Sherco Unit 2; Sherco Unit 2 Other |
710 MW | In study |
Sherburne, MN | MISO |
Dec 2022 | 2024 |
Replacing 615 MW Coal with 615 MW BESS; Campbell Units 1 & 2 Other |
615 MW | In study |
| MISO |
Jun 2024 | target 2028 |
Other project J2694, Christian County Other |
500 MW | In study |
Christian, IL | MISO |
Sep 2022 | target 2027 |
Other project J1488, Randolph County Other |
500 MW | Agreement signed |
Randolph, MO | MISO |
Apr 2019 | target 2024 |
Other project J2171, Perry County Other |
500 MW | In study |
Perry, IL | MISO |
Mar 2022 | target 2024 |
Other project J3163, Cass County Other |
479 MW | In study |
Cass, ND | MISO |
Jul 2022 | target 2028 |
Replacing 300 MW of existing coal generation with BESS; Edgewater 5 Other |
423 MW | In study |
| MISO |
Feb 2022 | target 2025 |
Surplus; Glacier Moraine Other |
360 MW | In study |
Cumberland, IL | MISO |
Jul 2024 | target 2027 |
Replace 330 MW of CLECO.DPS Unit with solar; Dolet Hills Other |
330 MW | In study |
De Soto Parish, LA | MISO |
Dec 2020 | target 2024 |
Replacing 106 MW Coal with 106 MW BESS; Edwards Unit 3 Other |
322 MW | In study |
Peoria, IL | MISO |
Jul 2024 | target 2025 |
Replacing 303.5 MW BESS with 303.5 MW COAL; Edgewater Unit 5 Other |
304 MW | In study |
Sheboygan, WI | MISO |
Dec 2024 | target 2025 |
Surplus; EAI.AECCO SWCT1 Other |
300 MW | In study |
Lonoke, AR | MISO |
Jun 2025 | target 2028 |
Other project J2691, Bollinger County Other |
250 MW | In study |
Bollinger, MO | MISO |
Sep 2022 | target 2027 |
Replacing 220 MW of coal generation with BESS; Trenton Channel 9 Other |
220 MW | In study |
Wayne, MI | MISO |
Oct 2023 | target 2025 |
Replacing 30 MW of existing coal generation with BESS at Burlington Generation Station; Burlington 5 Other |
212 MW | In study |
Des Moines, IA | MISO |
Feb 2022 | target 2024 |
Surplus; J834 Other |
200 MW | In study |
Phillips, AR | MISO |
Feb 2025 | target 2027 |
Surplus; J1450 Other |
150 MW | In study |
Webster, KY | MISO |
Feb 2025 | target 2026 |
Surplus; J1062 Other |
150 MW | In study |
Washtenaw, MI | MISO |
Oct 2024 | target 2027 |
Surplus; J875 Other |
150 MW | In study |
Lenawee, MI | MISO |
Oct 2024 | target 2027 |
Surplus; Shelby Other |
150 MW | In study |
Cumberland, IL | MISO |
Jun 2024 | target 2026 |
Surplus; J1320 Other |
150 MW | In study |
Branch, MI | MISO |
Aug 2024 | target 2026 |
Surplus; J806 Other |
149 MW | In study |
Calhoun, MI | MISO |
| target 2026 |
Other project J3400, Deuel County Other |
142 MW | In study |
Deuel, SD | MISO |
Mar 2024 | target 2028 |
Replacing 135.5 MW with 135.5 MW BESS; Blue Lake Units 1 2 4 Other |
136 MW | In study |
Scott, MN | MISO |
May 2024 | target 2027 |
Surplus; J33/J734 Other |
135 MW | In study |
Ford, IL | MISO |
May 2023 | target 2026 |
Surplus; J734 Other |
135 MW | In study |
Mclean, IL | MISO |
Dec 2022 | target 2026 |
Replacing 124.4 MW of existing gas generation with solar at Woodruff County (formerly Bailey); Woodruff Co Solar Other |
124 MW | In study |
| MISO |
Feb 2022 | 2024 |
Surplus; J1734 Other |
120 MW | In study |
Lee, IA | MISO |
Nov 2024 | target 2025 |
Surplus; J442 Other |
120 MW | In study |
Codington, SD | MISO |
Oct 2023 | target 2026 |
Surplus; G736 Other |
120 MW | In study |
Codington, SD | MISO |
Oct 2023 | target 2026 |
Surplus; J199/J202 Other |
100 MW | In study |
Tuscola, MI | MISO |
Jul 2024 | target 2013 |
Surplus; J909 Other |
100 MW | In study |
Tangipahoa Parish, LA | MISO |
Jan 2025 | target 2027 |
Surplus; J947 Other |
100 MW | In study |
| MISO |
Apr 2022 | target 2023 |
Surplus; Polaris Solar Other |
100 MW | Agreement signed |
Gratiot, MI | MISO |
Apr 2022 | target 2023 |
replacing 100MW of un-built solar with BESS; Mayhew Other |
100 MW | In study |
Benton, MN | MISO |
Nov 2023 | target 2025 |
Surplus; J1314 Other |
100 MW | In study |
Polk, WI | MISO |
Sep 2022 | target 2025 |
Surplus; J385 Other |
100 MW | In study |
Chisago, MN | MISO |
Jul 2024 | target 2026 |
Surplus; J758 Other |
100 MW | In study |
Calhoun, MI | MISO |
Aug 2024 | target 2027 |
Other project J4183 Other |
99.9 MW | In study |
| MISO |
| target 2027 |
Replacing 95 MW of coal with BESS; Meramec 1, 2, 3, 4 Other |
98.8 MW | In study |
St. Louis, MO | MISO |
Dec 2024 | target 2025 |
Surplus; J728 Other |
90.0 MW | In study |
Isabella, MI | MISO |
Aug 2022 | target 2025 |
Surplus; J717 Other |
90.0 MW | In study |
Isabella, MI | MISO |
Aug 2022 | target 2025 |
Surplus; J1224/J1329 Other |
85.1 MW | In study |
Washtenaw, MI | MISO |
Oct 2024 | target 2028 |
Surplus; Old Gold Other |
80.0 MW | In study |
Worth, IA | MISO |
Jun 2024 | target 2029 |
Surplus; Pine River Solar Other |
80.0 MW | Agreement signed |
Gratiot, MI | MISO |
Apr 2022 | target 2023 |
Surplus; J986 Other |
75.0 MW | In study |
| MISO |
Apr 2022 | target 2022 |
Surplus; J878 Other |
60.0 MW | In study |
| MISO |
Apr 2021 | 2024 |
Surplus; J1067 Other |
60.0 MW | In study |
White, IN | MISO |
May 2022 | 2024 |