United States › Grid › Interconnection queues › Kentucky
OTHER · MISOSurplus; J1450
Surplus; J1450 is a 150 MW other request in interconnection study in the MISO interconnection queue, in Webster County, Kentucky, connecting to BIG RIVERS ELECTRIC CORPORATION.
Queue statusIn planning
- PlanningQueued Feb 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Aug 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- S1073
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- BIG RIVERS ELECTRIC CORPORATION
- Connection point (POI)
- Hopkins to Reid EVH 161kV
- Location
- Webster County, Kentucky
- Technology
- Other: 150 MW · Battery
- Total requested
- 150 MW
- Queue status
- Active
- Entered queue
- 19 February 2025
- Proposed online date
- August 2026
Location
Marker shows the centre of Webster County; the queue data does not give exact sites.
Other requests in Webster County
- Solar project J1450, Webster CountySolar · 150 MW · agreement signed
- Solar project J1619, Webster CountySolar · 160 MW · in study
- Gas project J3089, Webster CountyGas · 696 MW · withdrawn
- Battery storage project J1901, Webster CountyBattery storage · 200 MW · withdrawn
- Solar project LGE-GIS-2019-005, Webster CountySolar · 80.0 MW · withdrawn
- Battery storage project J3033, Webster CountyBattery storage · 75.0 MW · withdrawn
- Solar project J1703, Webster CountySolar · 74.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem