SOLAR Β· SOUTHEASTSolar project LGE-GIS-2019-005, Webster County
Solar project LGE-GIS-2019-005, Webster County is a 80.0 MW solar request withdrawn in the Southeast interconnection queue, in Webster County, Kentucky, connecting to Louisville Gas & Electric and Kentucky Utilities Energy.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2019 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- LGE-GIS-2019-005
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Louisville Gas & Electric and Kentucky Utilities Energy
- Connection point (POI)
- Green River βΓΓ¬ Corydon Tap 161 kV line
- Location
- Webster County, Kentucky
- Technology
- Solar: 80.0 MW
- Total requested
- 80.0 MW
- Service type
- NRIS and ERIS
- Queue status
- Withdrawn
- Entered queue
- 13 March 2019
- Proposed online date
- December 2021
Location
Marker shows the centre of Webster County; the queue data does not give exact sites.
Other requests in Webster County
- Solar project J1450, Webster CountySolar Β· 150 MW Β· agreement signed
- Solar project J1619, Webster CountySolar Β· 160 MW Β· in study
- Surplus; J1450Other Β· 150 MW Β· in study
- Gas project J3089, Webster CountyGas Β· 696 MW Β· withdrawn
- Battery storage project J1901, Webster CountyBattery storage Β· 200 MW Β· withdrawn
- Battery storage project J3033, Webster CountyBattery storage Β· 75.0 MW Β· withdrawn
- Solar project J1703, Webster CountySolar Β· 74.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem