United States › Grid › Interconnection queues › Kentucky
SOLAR · MISOSolar project J1450, Webster County
Solar project J1450, Webster County is a 150 MW solar request with a signed interconnection agreement in the MISO interconnection queue, in Webster County, Kentucky, connecting to BIG RIVERS ELECTRIC CORPORATION.
Queue statusConsented
- PlanningQueued Apr 2019 (completed)
- ConsentedDec 2025 (current stage)
- Construction (not yet reached)
- OperatingTarget Aug 2025 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J1450
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- BIG RIVERS ELECTRIC CORPORATION
- Connection point (POI)
- Hopkins - Reid161kV Line
- Location
- Webster County, Kentucky
- Technology
- Solar: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 29 April 2019
- Agreement signed
- 18 December 2025
- Proposed online date
- August 2025
- Withdrawn
- August 2025
Location
Marker shows the centre of Webster County; the queue data does not give exact sites.
Other requests in Webster County
- Solar project J1619, Webster CountySolar · 160 MW · in study
- Surplus; J1450Other · 150 MW · in study
- Gas project J3089, Webster CountyGas · 696 MW · withdrawn
- Battery storage project J1901, Webster CountyBattery storage · 200 MW · withdrawn
- Solar project LGE-GIS-2019-005, Webster CountySolar · 80.0 MW · withdrawn
- Battery storage project J3033, Webster CountyBattery storage · 75.0 MW · withdrawn
- Solar project J1703, Webster CountySolar · 74.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem