United States › Grid › Interconnection queues

OTHER · MISO

Replacing 615 MW Coal with 615 MW BESS; Campbell Units 1 & 2

Replacing 615 MW Coal with 615 MW BESS; Campbell Units 1 & 2 is a 615 MW other request in interconnection study in the MISO interconnection queue, connecting to METC.

Queue statusIn planning
  1. PlanningQueued Jun 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
R1052
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
"18CAMPBELLW”, “18CAMPBELLB
Technology
Other: 615 MW · Battery
Total requested
615 MW
Service type
Energy only (ERIS)
Queue status
Active
Entered queue
24 June 2024
Proposed online date
March 2028

Location

No county location in the queue data.

Power plants in · Transmission lines in