Surplus; J199/J202

Surplus; J199/J202 is a 100 MW other request in interconnection study in the MISO interconnection queue, in Tuscola County, Michigan, connecting to ITC.

Queue statusIn planning
  1. PlanningQueued Jul 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2013 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
S1059
Grid region
MISO (Midcontinent)
Utility / transmission owner
ITC
Connection point (POI)
Dixon 120kV - Bus # 265182
Location
Tuscola County, Michigan
Technology
Other: 100 MW · Battery
Total requested
100 MW
Queue status
Active
Entered queue
26 July 2024
Proposed online date
November 2013

Location

Marker shows the centre of Tuscola County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Tuscola County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem