United States › Grid › Interconnection queues › Michigan

SOLAR · MISO

Solar project J2578, Tuscola County

Solar project J2578, Tuscola County is a 180 MW solar request in interconnection study in the MISO interconnection queue, in Tuscola County, Michigan, connecting to METC.

Queue statusIn planning
  1. PlanningQueued Sep 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J2578
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
KARN - THETFORD (ATLANTA) 138.0kV
Location
Tuscola County, Michigan
Technology
Solar: 180 MW
Total requested
180 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Active
Entered queue
13 September 2022
Proposed online date
September 2026

Location

Marker shows the centre of Tuscola County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Tuscola County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem