United States › Grid › Interconnection queues › Michigan

ONSHORE WIND · MISO

Onshore wind project J161, Tuscola County

Onshore wind project J161, Tuscola County is a 155 MW onshore wind request built and operating in the MISO interconnection queue, in Tuscola County, Michigan.

Queue statusOperating
  1. PlanningQueued Aug 2010 (completed)
  2. ConsentedJun 2013 (completed)
  3. Construction (completed)
  4. OperatingApr 2012 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
J161
Grid region
MISO (Midcontinent)
Connection point (POI)
Bauer - Rapson 345 kV
Location
Tuscola County, Michigan
Technology
Wind: 155 MW
Total requested
155 MW
Study phase
DPP - SIS
Queue status
Operational
Entered queue
31 August 2010
Agreement signed
21 June 2013
Proposed online date
April 2012
Came online
April 2012

Location

Marker shows the centre of Tuscola County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Tuscola County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem