Surplus; J875

Surplus; J875 is a 150 MW other request in interconnection study in the MISO interconnection queue, in Lenawee County, Michigan, connecting to METC.

Queue statusIn planning
  1. PlanningQueued Oct 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
S1066
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Location
Lenawee County, Michigan
Technology
Other: 150 MW · Battery
Total requested
150 MW
Queue status
Active
Entered queue
7 October 2024
Proposed online date
September 2027

Location

Marker shows the centre of Lenawee County; the queue data does not give exact sites.